Project Timeline


Project Timeline
Public announcement of project March 2009
Commencing community consultation April 2009
Permitting and environmental approvals March 2009 - March 2010
Engineering June 2009 - January 2012
(95% completion)
Construction contract arrangements finalised February 2010
Financial close September 2010
Field construction start November 2010
Mechanical completion April 2013
Startup begins June 2013
Full production November 2013